Earned Value Management and Project Performance Metrics

Posted in management by Christopher R. Wirz on Wed Mar 25 2015

Industry emphasizes Earned Value Management (EVM) as a comprehensive methodology for measuring project performance by integrating scope, schedule, and cost data. EVM provides objective metrics that reveal whether a project is on track, overspending, or falling behind—enabling proactive corrective action.

Core Earned Value Metrics

Three Fundamental Values:

Planned Value (PV) - The authorized budget assigned to scheduled work. This is what you planned to spend by a given point in time. Also called Budgeted Cost of Work Scheduled (BCWS).

Earned Value (EV) - The value of work actually completed, measured against the budget. This represents what was actually accomplished. Also called Budgeted Cost of Work Performed (BCWP).

Actual Cost (AC) - The actual expenditure incurred for work performed. This is what you've actually spent. Also called Actual Cost of Work Performed (ACWP).

Key Performance Indicators

Cost Performance Index (CPI)

  • Formula: CPI = EV / AC
  • Meaning: Cost efficiency - how much value you're getting for each dollar spent
  • Interpretation:
    • CPI > 1.0 = Under budget (good)
    • CPI = 1.0 = On budget
    • CPI < 1.0 = Over budget (poor)
  • Example: CPI of 0.85 means you're getting $0.85 of value for every $1.00 spent (15% over budget)

Schedule Performance Index (SPI)

  • Formula: SPI = EV / PV
  • Meaning: Schedule efficiency - how much progress you're making compared to the plan
  • Interpretation:
    • SPI > 1.0 = Ahead of schedule (good)
    • SPI = 1.0 = On schedule
    • SPI < 1.0 = Behind schedule (poor)
  • Example: SPI of 1.15 means you've completed 15% more work than planned at this point

Cost Variance (CV)

  • Formula: CV = EV - AC
  • Meaning: Absolute cost difference from budget
  • Interpretation:
    • CV > 0 = Under budget (good)
    • CV = 0 = On budget
    • CV < 0 = Over budget (poor)

Schedule Variance (SV)

  • Formula: SV = EV - PV
  • Meaning: Absolute schedule difference from plan (in dollar terms)
  • Interpretation:
    • SV > 0 = Ahead of schedule (good)
    • SV = 0 = On schedule
    • SV < 0 = Behind schedule (poor)

Variance at Completion (VAC)

  • Formula: VAC = BAC - EAC
  • Meaning: Expected variance from original budget at project completion
  • Interpretation:
    • VAC > 0 = Expecting to finish under budget
    • VAC = 0 = Expecting to finish on budget
    • VAC < 0 = Expecting to finish over budget
  • Use: Helps stakeholders understand final cost impact

Forecasting Metrics

Budget at Completion (BAC)

  • The total planned budget for the entire project
  • Established during planning and serves as the baseline

Estimate at Completion (EAC)

  • The expected total cost when the project is finished
  • Multiple formulas depending on assumptions:

EAC Formulas:

  1. EAC = AC + Bottom-up ETC (most accurate, requires detailed re-estimation)
  2. EAC = BAC / CPI (assumes current cost efficiency continues)
  3. EAC = AC + (BAC - EV) (assumes remaining work will be on budget)
  4. EAC = AC + [(BAC - EV) / (CPI × SPI)] (considers both cost and schedule performance)

Estimate to Complete (ETC)

  • Formula: ETC = EAC - AC
  • Meaning: How much more money is needed to finish the project
  • Use: Critical for resource planning and funding requests

To-Complete Performance Index (TCPI)

  • Formula for remaining funds: TCPI = (BAC - EV) / (BAC - AC)
  • Formula for EAC: TCPI = (BAC - EV) / (EAC - AC)
  • Meaning: The cost efficiency required to meet budget goals
  • Interpretation:
    • TCPI > 1.0 = Must improve cost performance to meet target
    • TCPI = 1.0 = Can maintain current performance
    • TCPI < 1.0 = Can perform worse and still meet target

Schedule Metrics

Critical Path Method (CPM)

  • Identifies the longest path through the project network
  • Determines minimum project duration
  • Activities on critical path have zero float/slack

Float/Slack

  • Total Float: Amount an activity can be delayed without delaying project
  • Free Float: Amount an activity can be delayed without delaying successor activities

Schedule Performance Index - Time-based (SPI(t))

  • Alternative SPI calculation using time units instead of cost
  • More accurate for schedule assessment late in projects

Additional Performance Metrics

Percent Complete

  • Physical progress measurement (50% of work completed)
  • Critical for calculating earned value

Percent Spent

  • Financial expenditure percentage (50% of budget spent)
  • Used with percent complete to assess efficiency

Cost Performance Baseline

  • Time-phased budget used to measure, monitor, and control cost performance
  • Often displayed as an S-curve

Performance Measurement Baseline (PMB)

  • Integrated scope, schedule, and cost baseline
  • Used as reference for EVM measurements

Management Reserve

  • Budget set aside for unknown risks (unknown unknowns)
  • Not included in performance measurement baseline
  • Requires management approval to use

Contingency Reserve

  • Budget for known risks (known unknowns)
  • Included in performance measurement baseline
  • Project manager can use as needed

Practical Application Example

Project Status at Month 6:

  • BAC = $1,000,000
  • PV = $500,000 (planned to complete 50% by now)
  • EV = $400,000 (actually completed 40%)
  • AC = $450,000 (actually spent)

Calculations:

  • CPI = $400,000 / $450,000 = 0.89 (11% over budget)
  • SPI = $400,000 / $500,000 = 0.80 (20% behind schedule)
  • CV = $400,000 - $450,000 = -$50,000 (over budget)
  • SV = $400,000 - $500,000 = -$100,000 (behind schedule)
  • EAC = $1,000,000 / 0.89 = $1,123,596 (projected final cost)
  • VAC = $1,000,000 - $1,123,596 = -$123,596 (projected overrun)
  • TCPI = ($1,000,000 - $400,000) / ($1,000,000 - $450,000) = 1.09

Interpretation: The project is significantly behind schedule and over budget. To finish within the original budget, cost performance must improve to 1.09 (9% better than current 0.89), which is unlikely. Project requires corrective action.

Benefits of EVM

  • Objective measurement - Not based on opinions or feelings
  • Early warning system - Identifies problems before they become critical
  • Integrated view - Combines scope, schedule, and cost
  • Trend analysis - Tracks performance over time
  • Forecasting - Predicts final outcomes based on current performance
  • Standardized reporting - Common language for stakeholders
  • Actionable data - Supports decision-making and corrective actions

Limitations and Considerations

  • Requires accurate work progress measurement
  • Works best with clear, measurable deliverables
  • Less effective in highly uncertain environments
  • Can be administratively intensive
  • May encourage focus on metrics over value
  • SPI becomes less meaningful near project end
  • Doesn't capture quality or stakeholder satisfaction

Key Concepts

Earned Value Management (EVM) - Methodology integrating scope, schedule, and cost data to objectively measure project performance and progress.

Planned Value (PV) - Authorized budget assigned to scheduled work; what you planned to spend by a point in time. Also called BCWS.

Earned Value (EV) - Budgeted value of work actually completed; what you've accomplished measured in budget terms. Also called BCWP.

Actual Cost (AC) - Real expenditure incurred for work performed; what you've actually spent. Also called ACWP.

Cost Performance Index (CPI) - Ratio of earned value to actual cost (EV/AC); measures cost efficiency where >1.0 is under budget.

Schedule Performance Index (SPI) - Ratio of earned value to planned value (EV/PV); measures schedule efficiency where >1.0 is ahead of schedule.

Cost Variance (CV) - Difference between earned value and actual cost (EV - AC); positive values indicate under budget performance.

Schedule Variance (SV) - Difference between earned value and planned value (EV - PV); positive values indicate ahead of schedule performance.

Budget at Completion (BAC) - Total planned budget for the entire project; the baseline budget.

Estimate at Completion (EAC) - Expected total cost when all work is finished; forecasted final project cost.

Estimate to Complete (ETC) - Expected cost to finish all remaining work (EAC - AC); funds still needed.

Variance at Completion (VAC) - Expected variance from original budget at completion (BAC - EAC); projected over/under budget amount.

To-Complete Performance Index (TCPI) - Required cost efficiency to achieve budget goals; shows how efficiently remaining work must be performed.

Performance Measurement Baseline (PMB) - Integrated scope, schedule, and cost baseline against which project performance is measured.

Cost Performance Baseline - Time-phased budget used to measure and monitor cost performance, typically displayed as S-curve.

Budgeted Cost of Work Scheduled (BCWS) - Older term for Planned Value (PV).

Budgeted Cost of Work Performed (BCWP) - Older term for Earned Value (EV).

Actual Cost of Work Performed (ACWP) - Older term for Actual Cost (AC).

Critical Path - Longest sequence of dependent activities determining minimum project duration; activities with zero float.

Critical Path Method (CPM) - Technique for scheduling project activities using network diagrams and calculating critical path.

Float (Slack) - Amount of time an activity can be delayed without delaying the project or successors.

Total Float - Amount an activity can be delayed without delaying the overall project completion date.

Free Float - Amount an activity can be delayed without delaying any successor activity's early start date.

Management Reserve - Budget for unidentified risks (unknown unknowns); not part of performance baseline, requires management approval.

Contingency Reserve - Budget for identified risks (known unknowns); part of performance baseline, controlled by project manager.

S-Curve - Graphical display of cumulative costs, labor hours, or other quantities over time; typical project expenditure pattern.

Percent Complete - Estimate of work physically completed on an activity or project, used to calculate earned value.

Percent Spent - Portion of budget already expended, used to assess cost efficiency against percent complete.

Baseline - Approved version of a work product used as basis for comparison to actual results.

Variance Analysis - Technique for determining cause and degree of difference between baseline and actual performance.

Trend Analysis - Examination of project performance over time to determine if performance is improving or deteriorating.

Forecasting - Estimating future project conditions and events based on current performance and historical information.

Performance Report - Document presenting performance information including status, progress, and forecasts.

Work Performance Data - Raw observations and measurements collected during project execution.

Work Performance Information - Performance data analyzed and integrated based on context and relationships.

Work Performance Reports - Physical or electronic representation of performance information intended for decision-making.

Control Account - Management control point where scope, budget, actual cost, and schedule are integrated for performance measurement.

Work Package - Lowest level of WBS for which cost and duration are estimated and managed; deliverable at lowest decomposition level.

Planning Package - WBS component below control account but above work package, with known work content but without detailed schedule.

Level of Effort (LOE) - Support-type activity that does not produce definite deliverables (e.g., project management, quality assurance).

Apportioned Effort - Activity directly related to measurable discrete work, earned in same proportion (e.g., inspection).

Discrete Effort - Activity that produces specific deliverables and can be directly planned and measured.

50/50 Rule - Earned value technique crediting 50% EV at start of work and 50% at completion.

0/100 Rule - Earned value technique crediting 100% EV only upon complete task completion.

Weighted Milestone - Earned value technique assigning earned value credit based on achievement of milestones.

Percent Complete Method - Earned value technique based on estimates of work completed (physical or subjective).

Units Complete Method - Earned value technique for repetitive work, earning value based on completed units.

Cost-Schedule Index (CSI) - Combined indicator calculated as CPI × SPI; measures overall project health.

Schedule Performance Index - Time (SPI(t)) - Alternative schedule index using time periods rather than cost; more accurate late in projects.

Independent Estimate at Completion (IEAC) - EAC calculated independently by analysts, not derived from project team data.

Latest Revised Estimate (LRE) - Most current estimate of final project cost, may differ from calculated EAC.

Milestone - Significant point or event in the project, typically with zero duration, used to track progress.

Variance Threshold - Predetermined acceptable range of variance before corrective action is required.

Control Limit - Boundary of common cause variation on control chart; exceeding indicates special cause requiring investigation.

Root Cause Analysis - Technique for identifying underlying reasons for variances or problems.

Corrective Action - Intentional activity to realign future project performance with the plan.

Preventive Action - Intentional activity to ensure future project performance aligns with the plan.

Defect Repair - Intentional activity to modify a nonconforming product or component.